Drawings for the Chickamauga Project
Tennessee Valley Authority | 1948
TVA Engineering and Construction Departments
Digital Donation by Chuck Chamberlain III
GENERAL
1
Map and Profile of the Tennessee Valley 453A95
2
Elevation, and Sections of Powerhouse, Dam, and Lock 10B208
3
Dam - Transportation Facilities 30K262
ARCHITECTURE AND LANDSCAPING
4
Powerhouse - Architectural - Downstream Elevation 46W300
5
Powerhouse - Architectural - Upstream Elevation 46W301
6
Powerhouse - Architectural - North and South Elevations 46W302
NAVIGATION LOCK
7
General Plan 3/1
8
Lock Walls - Plan - Upper End 20/1
9
Lock Walls - Plan - Lower End 20/2
10
Lock Walls - Sections 20/5
11
Lock Walls - Sections 20/6
12
Lock Walls - Culverts - Upper End 20/9
14
Lower Lock Gate - Downstream Elevation - Upper Part 21/13
15
Lower Lock Gate - Downstream Elevation - Lower Part 21/14
16
Lower Lock Gate - Top and Bottom Arch Ribs 21/15
17
Segmental Valve - Design Data and Assembly 25/1
18
Electrical System - One Line Diagram 29/8
19
Lock Wall Extension - Concrete - Outline and Reinforcement,
EARTH EMBANKMENTS
20
North Embankment and Diversion Canal - Toe Drainage 22N218
21
North Embankment and Diversion Canal - General Plan and Sections 22N222
22
North Embankment and Diversion Canal - Cross Sections 22N223
23
South Embankment - General Plan 23N200
24
South Embankment - Cross Sections 23N201
25
South Embankment - Drainage - Plan and Profile 23N209
FOREBAY, TAILRACE, AND BULKHEAD WALLS
26
Powerhouse Substructure - Service Bay - Concrete - Forebay, Tailrace, and Bulkhead Retaining Walls - Outline 41N300
SPILLWAY DAM
27
Dam - General Plan and Sections 51N200
28
Dam - Foundation Grouting and Drainage 51N201
29
Dam - Concrete - Typical Pier and Weir Outline, Sheet 1 51N203
30
Dam - Concrete - Typical Pier Outline, Sheet 1 51N206
31
Dam - Concrete - Operating Bridge Deck - Outline and Reinforcement, Sheet 1 51N208
32
Dam - Concrete - Operating Bridge Deck - Outline and Reinforcement, Sheet 2 51N209
33
Dam - Concrete - Pier Reinforcement, Sheet 1 51N211
34
Dam - Concrete - Pier Reinforcement, Sheet 2 51N212
35
Dam - Concrete - Pier 1 and Junction with Lock - Outline, Sheet 1 51N217
36
Dam - Concrete - Pier 1 and Junction with Lock - Outline, Sheet 2 51N218
37
Dam - Concrete - Apron Outline and Reinforcement 51N255
38
Dam - Concrete - Grout and Water Seals 51N260
39
Gates - Top and Bottom Sections - Assembly 14N301
40
Gates - Bottom Section - Structural Details 14N303
41
Gate Dogging Mechanism - Arrangement 14N310
42
Intake and - Gantry Cranes - Lifting Beam Arrangement - General Assembly 14N313
POWERHOUSE INTAKE
43
Gates - Assembly 14N201
44
Wheeled Gates - Structural Details 14N202
45
Gates - Seals, Sheet 1 14N206
46
Gate Dogging Mechanism - Arrangement 14N212
47
Concrete - End Piers - Reinforcement 31N215
48
Unit 1 - Concrete - Top Slab - Reinforcement, Sheet 1 31N223
49
Unit 1 - Concrete - Top Slab - Reinforcement, Sheet 2 31N224
50
Units 1 and 2 - Concrete - Gate Pit and Deck - Upstream Wall - Reinforcement 31N230
51
Unit 1 - Concrete - Gate Pit and Deck - Downstream Wall - Reinforcement 31N232
POWERHOUSE
52
Equipment - Plan - El. 630.0 46W400
53
Equipment - Plan - El. 649.0 46W401
54
Equipment - Plan - El. 665.0 46W402
55
Equipment - Plan - El. 680.0 46W403
56
Equipment - Plan - El. 694.0 46W404
57
Equipment - Plans - El. 711.0 and El. 726.0 46W405
58
Equipment - Roof and Deck Plan 46W406
59
Equipment - Transverse Section on Center Line of Unit 1 46W407
60
Equipment - Transverse Section Through Service Bay 46W408
63
Equipment - Longitudinal Section Through Electrical Bay 46W411
64
Foundation Grouting and Drainage 46N220
65
Substructure - Units 1, 2, and 3 - Concrete - Arrangement of Pours, Sheet 1 41N215
66
Substructure - Units 1, 2, and 3 - Concrete - Arrangement of Pours, Sheet 2 41N216
67
Substructure - Units 1, 2, and 3 - Concrete - Scroll Case - Outline, Sheet 1 41N245
68
Substructure - Units 1, 2, and 3 - Concrete - Scroll Case - Outline, Sheet 2 41N246
69
Substructure - Units 1, 2, and 3 - Concrete - Scroll Case - Outline, Sheet 3 41N247
70
Substructure - Unit 4 - Concrete - Outline, Sheet 1 41N250
71
Substructure - Unit 4 - Concrete - Outline, Sheet 2 41N251
72
Substructure - Units 1, 2, and 3 - Concrete - Scroll Case Neat Lines - Plan and Sections 41N264
73
Substructure - Units 1, 2, and 3 - Concrete - Lower Speed Ring and Draft Tube Liner Erection 41N280
74
Substructure - Service Bay - Concrete - General Plan and Sections - Outline 41N3.50
75
Service Bay and Units 1, 2, and 3 - Valve Operation Diagram - Governor and Lubricating Oil System 47N757
76
Service Bay, Intake, and Switchyard - Valve Operation Diagram - Raw Water System 47N758
77
Service Bay, Intake, and Units 1, 2, and 3 - Valve Operation Diagram - Compressed Air System 47N759
78
General - Valve Operation Diagram - Treated Water System 47N760
79
Service Bay and Units 1, 2, and 3 - Valve Operation Diagrams - Miscellaneous Systems 47N762
80
General - Valve Operation Diagram - Drawing Index, Symbols, and Valve Marker Tag Nomenclature 47N763
POWERHOUSE
81
Wiring Diagrams - Development Single Line Diagram 45N501
82
Wiring Diagrams - Main Single Line 45N502
83
Wiring Diagrams - 44- and 110-Kv Feeders Single Line Diagram 45N504
84
Wiring Diagrams - Telephone System - Single Line 45N508
85
Wiring Diagrams - Code Call - Single Line 45N510
86
Switchboards - Main Control Benchboard - Front Elevation 45N601
87
Switchboards - Main Instrument Board - Front Elevation 45N603
88
Switchboards - Main Relay Board - Front Elevation 45N605
89
Switchboards - Recording Instrument Board - Elevations 45N606
90
Auxiliary Boards and Wiring - A-C Main Auxiliary Power Boards - Outline and General Arrangement 45N700
91
Auxiliary Boards and Wiring - A-C Unit Auxiliary Power Boards - Outline and General Arrangement 45N702
92
Auxiliary Boards and Wiring - A-C Common Auxiliary Power Board - Outline and General Arrangement 45N704
93
Auxiliary Boards and Wiring - A-C Lighting and Heating Power Board - Outline and General Arrangement 45N706
94
Switchboards - Battery Board 45N708
95
Auxiliary Boards and Wiring - Air Conditioning Power Board - Outline and General Arrangement 45N716
96
Wiring Diagrams - A-C Auxiliary Power - Single Line Diagram 45N724
97
Wiring Diagrams - Lighting and Heating System - Single Line 45N728
98
Wiring Diagrams - COâ‚‚ Systems - Schematic Diagram 45N736
SWITCHYARD
99
General Layout - Powerhouse, Switchyard, and Adjacent Areas 71N200
100
Powerhouse, Service Bay, and Valve Operation Diagram - Insulating Oil System 47N761
101
Concrete - Cable Tunnel - Outline and Reinforcement, Sheet 1 71N207
102
Concrete - Cable Tunnel - Outline and Reinforcement, Sheet 5 71W213
103
Electrical - General Arrangement Plan 75N200
104
154-Kv Structure - Electrical Equipment - Typical Cross Section - Main Transformer Bay 75N216
105
154-Kv Structure - Electrical Equipment - Typical Cross Section - 154-Kv Feeder Bay 75N218
106
154-Kv Structure - Electrical Equipment - Longitudinal Elevations 75N220
CONSTRUCTION OPERATIONS
107
General - Construction Schedule K11349
108